Question: A project analyst (or team) has determined that a particular project task could be completed in a minimum of 20 days, most likely 90 days,
A project analyst (or team) has determined that a particular project task could be completed in a minimum of 20 days, most likely 90 days, or a maximum of 100 days.
Determine the probability/likelihood the task will take: a. more than 80 days b. less than 40 days.