Question: A project analyst (or team) has determined that a particular project task could be completed in a minimum of 20 days, most likely 90 days,

A project analyst (or team) has determined that a particular project task could be completed in a minimum of 20 days, most likely 90 days, or a maximum of 100 days.

Determine the probability/likelihood the task will take:

a. more than 80 days

b. less than 40 days

Please send me answer in typed form strictly prohibited handwritten solution.