Question: A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. The estimated time along the critical path is

A project being analyzed by PERT has 38
A project being analyzed by PERT has 38
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. The estimated time along the critical path is 90 days with a project variance of 20 What due date wil give the projoct a 0.85 probability of completion? Select the tange that includes the corresponding completion time in days. Standard Normal Table between 100.5 days and 105.5 days more than 105.5 days between 95.5 days and 100.5 days between 90 days and 95.5 days