Question: A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in less than 88 or more than 93 days?

A) 0.7257

B) 0.3811

C) 0.9772

D) 0.3446

E) 0.6189

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!