Question: A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 89 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?