Question: A project being analyzed by PERT has 4 5 activities, 2 5 of which are on the critical path. If the estimated time along the

A project being analyzed by PERT has 45 activities, 25 of which are on the critical path. If the estimated time along the critical path is 400 days with a project variance of 120, what is the probability that the project will be completed in 420 days or less?
Answers:
0.9660