Question: A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project a 19% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.)
Group of answer choices
from 111.76 to 111.88 days
from 111.64 to 111.76 days
from 111.88 to 112 days
from 112 to 112.12 days
from 112.12 to 112.24 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
