Question: A project being analyzed by PERT has 6 0 activities, 1 3 of which are on the critical path. If the estimated time along the

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 210 days with a project variance of 64, what is the probability that the project will take less than 220 days to complete?
Normal Curve Areas.pdf
Group of answer choices
1.25
0.10565
0.89435
0.56208
0.84134

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!