Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 60

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 234 days with a project variance of 100 , what is the probability that the project will take less than 224 days to complete? A. near zero B. 0.1587 C. 0.0126 D. 2.14 E. 0.8413