Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 234 days with a project variance of 100, what is the probability that the project will take less than 224 days to complete?