Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 234 days with a project variance of 100, what is the probability that the project will take less than 224 days to complete? O A. 2.14 OB. 0.8413 O C. near Zero OD. 0.1587 O E. 0.0126