Question: A project comprises of activities A, B, C, D, E, F. The duration of project is 15 days. The duration for activity C is 4

A project comprises of activities A, B, C, D, E,
A project comprises of activities A, B, C, D, E, F. The duration of project is 15 days. The duration for activity C is 4 and it has the slack of 2 days. If activity C is delayed by 7 days (and all other activities are not delayed), then what is the new project duration