Question: A project comprises of activities A , B , C , D , E , F . The duration of project is 2 7 2

A project comprises of activities A, B, C, D, E, F. The duration of project is 272 days. The duration for activity D is 63 days and it has the slack of 11 days. Suppose activity D is delayed and no other activity is delayed. As a result of this delay in D, the project duration increased by 38 days.
What is the delay (in number of days) in activity D?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!