Question: A project comprises of activities A , B , C , D , E , F . The duration of project is 2 7 2
A project comprises of activities A B C D E F The duration of project is days. The duration for activity D is days and it has the slack of days. Suppose activity D is delayed and no other activity is delayed. As a result of this delay in D the project duration increased by days.
What is the delay in number of days in activity D