Question: A project comprises of activities A, B, C, D, E, F. The duration of project is 60 days. The duration for activity D is 15

A project comprises of activities A, B, C, D, E, F. The duration of project is 60 days. The duration for activity D is 15 days and it has the slack of 9 days. Suppose activity D is delayed by 17 days and no other activity is delayed. As a result of this delay in D, what is the new project duration