Question: A project comprises the activities shown in the Table below, which also shows the duration of each activity. Table 2: Activities and duration of project

A project comprises the activities shown in the Table below, which also shows the duration of each activity.

Table 2: Activities and duration of project

Duration in weeks

Activity

Preceding activity

Optimistic

Most likely

Pessimistic

A

-

2

3

3

B

-

10

12

15

C

A

4

5

8

D

B

2

2

2

E

A,D

3

3

3

F

B

3

4

5

G

C,E,F

8

10

20

H

G

2

3

5

I

G

2

2

2

J

H

4

5

10

K

I,J

2

4

6

Construct a network diagram for this project.

Calculate the expected completion tine and variance of all activities.

Determine the critical paths and all critical activities.

Determine the probability that the project will take less than 42 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!