Question: A project contains 4 paths. The expected duration (days) and variance for each path are shown below. Path Path Variance Path Expected Duration 10 ABCD

A project contains 4 paths. The expected duration

A project contains 4 paths. The expected duration (days) and variance for each path are shown below. Path Path Variance Path Expected Duration 10 ABCD 7.2 AXYZ 13 3.7 AGHI 6 2.1 AEFG 9 14.3 We expect the project will be completed within X days 95% of the time. What is X? 20.25 16.77 19.07 O 16.15 0 None of the answers provided are correct within 0.5 days