Question: . A project for improving a billing process has the following precedence relationships and activity limes: a. Choose the correct network diagram below. QA c.

. A project for improving a billing process has.

A project for improving a billing process has the following precedence relationships and activity limes: a. Choose the correct network diagram below. QA c. S S b. Calculate the slack for each activity. Which activities are on the critical path? Activity A B D E F G Activity Time (weeks) Immediate Predecessor(s) 3 11 A 13 B, C 10 B 6 D 5 E F.G Papo-i G O D. Activity Time (weeks) 3 11 7 13 10 6 5 8 Activity B I D E F G H S On critical path? Slack (weeks)