Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 - B
A project for improving a billing process has the following precedence relationships and activity times:
Activity Activity Time (weeks) Immediate Predecessor(s) A 2 - B 10 - C 5 A D 11 B, C E 11 B F 4 D G 8 E H 6 F, G
a. Choose the correct network diagram below.



b. Calculate the slack for each activity. Which activities are on the critical path?
A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Immediate Predecessor(s) Activity A 2 10 5 C D : 1 11 11 A B, C B D E F G 4 F G 8 H 6 a. Choose the correct network diagram below. OA. OB. B 10 O c. OD. Segon H S B 10 8 10 11 b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) 2 V 10 5 11 V IT m 000D E 11 F 4 G 8 H 6 Selected delimiter: Tab 2 10 B C D E F 5. ht B 11 11 4 8 6 , B D E F G GStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts