Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 B 7
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 2 | |
| B | 7 | |
| C | 6 | A |
| D | 14 | B, C |
| E | 11 | B |
| F | 4 | D |
| G | 3 | E |
| H | 6 | F, G |
Homework:Exercises LM 7 - Project Management
Question 2, Problem 3
Part 2 of 2
HW Score: 61.22%, 18.37 of 30 points
Points: 0.59 of 10
Save
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 2 | |
| B | 7 | |
| C | 6 | A |
| D | 14 | B, C |
| E | 11 | B |
| F | 4 | D |
| G | 3 | E |
| H | 6 | F, G |
Calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On critical path? | Slack (weeks) |
| A | 2 | Yes No | nothing |
| B | 7 | Yes No | nothing |
| C | 6 | Yes No | nothing |
| D | 14 | No Yes | nothing |
| E | 11 | Yes No | nothing |
| F | 4 | Yes No | nothing |
| G | 3 | Yes No | nothing |
| H | 6 | Yes No | nothing |