Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 B 7

A project for improving a billing process has the following precedence relationships and activity times:

Activity

Activity Time (weeks)

Immediate Predecessor(s)

A

2

B

7

C

6

A

D

14

B, C

E

11

B

F

4

D

G

3

E

H

6

F, G

Homework:Exercises LM 7 - Project Management

Question 2, Problem 3

Part 2 of 2

HW Score: 61.22%, 18.37 of 30 points

Points: 0.59 of 10

Save

A project for improving a billing process has the following precedence relationships and activity times:

Activity

Activity Time (weeks)

Immediate Predecessor(s)

A

2

B

7

C

6

A

D

14

B, C

E

11

B

F

4

D

G

3

E

H

6

F, G

Calculate the slack for each activity. Which activities are on the critical path?

Activity

Activity

Time (weeks)

On critical path?

Slack

(weeks)

A

2

Yes

No

nothing

B

7

Yes

No

nothing

C

6

Yes

No

nothing

D

14

No

Yes

nothing

E

11

Yes

No

nothing

F

4

Yes

No

nothing

G

3

Yes

No

nothing

H

6

Yes

No

nothing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!