| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 2 | |
| B | 12 | |
| C | 8 | A |
| D | 12 | B, C |
| E | 10 | B |
| F | 5 | D |
| G | 4 | E |
| H | 7 | F, G |