Question: A project for improving a biting process has the following procedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) 2 8 8 11

A project for improving a biting process has the
A project for improving a biting process has the following procedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) 2 8 8 11 9 B D E F G H A 4 7 7 B D E F,G a. Choose the correct network diagram below. OM 8 S S b. Calculate the slack for each activity. Which activities are on the critical pathi? Activity Activity Time (weeks) On critical path? Slack (weeks) B 8 D 11 E 9 F 4 G 7 H 7