A project has 7 activities P, Q, R, S, T, U, and V. Activity times and precedence relations are given below:

Activity Immediate predecessor(s) Activity time (days)
P - 9
Q - 7
R - 13
S P, Q 9
T Q,R 7
U S,T 2
V T 8

write down the answers for:

  1. the earliest finish time of Q

  2. the earliest finish time of S

  3. the earliest finish time of T

  4. the earliest finish time of U

  5. the latest start time of Q

  6. the latest start time of R

  7. the latest start time of S

  8. the latest start time of T