Question: A project has 9 tasks. Tasks A and B can be done at the same time at the start of the project. Task C can

A project has 9 tasks. Tasks A and B can be done at the same time at the start of the project.
Task C can start as soon as tasks A and B are complete. Task D can start as soon as task C is
complete. Tasks E and H can start as soon as task B is complete. Task F can start as soon as tasks
A and B are complete. Task G can start as soon as task F is complete. Task I can start as soon as
task H is complete. The project is completed when all tasks are completed.
a)Draw a task-on-link representation of this project below
 A project has 9 tasks. Tasks A and B can be