Question: A project has a task with the following task time estimates Pessimistic completion time 2 1 weeks Most likely completion time 1 6 weeks Optimistic

A project has a task with the following task time estimates Pessimistic completion time 21 weeks Most likely completion time16 weeks Optimistic completion time=5 weeks What is the Variance for the task?