Question: A project has a task with the following task time estimates: Pessimistic completion time = 21 weeks Most likely completion time = 16 weeks Optimistic

A project has a task with the following task time
A project has a task with the following task time estimates: Pessimistic completion time = 21 weeks Most likely completion time = 16 weeks Optimistic completion time - 5 weeks What is the variance for the task? OA) 16.6 weeks OB) 10.3 weeks OC) 8.9 weeks OD) 7.11 weeks