Question: A project has a task with the following task time estimates: Pessimistic completion time = 29 weeks Most likely completion time - 14 weeks Optimistic

A project has a task with the following task time
A project has a task with the following task time estimates: Pessimistic completion time = 29 weeks Most likely completion time - 14 weeks Optimistic completion time = 9 weeks What is the estimated completion time for the task? OA) 18.5 weeks OB) 12.3 weeks OC) 14.6 weeks OD) 15.7 weeks