Question: A project has a task with the following task time estimates: Pessimistic completion time = 18 weeks Most likely completion time = 15 weeks Optimistic
Pessimistic completion time = 18 weeks
Most likely completion time = 15 weeks
Optimistic completion time = 7 weeks.
What is the estimated completion time for the task?
Step by Step Solution
3.28 Rating (172 Votes )
There are 3 Steps involved in it
By using formula 121 we can calcula... View full answer