Question: A project has a task with the following task time estimates: Pessimistic completion time = 18 weeks Most likely completion time = 15 weeks Optimistic

A project has a task with the following task time estimates:
Pessimistic completion time = 18 weeks
Most likely completion time = 15 weeks
Optimistic completion time = 7 weeks.
What is the estimated completion time for the task?