Question: A project has activities A, B, C, D as its critical activities with A ->B -> C-> D as its critical path. The expected values
A project has activities A, B, C, D as its critical activities with A ->B -> C-> D as its critical path. The expected values and variances of activities A, B, C, D in weeks are:
A (exp value =15 , var = 3 );
B (exp value =14 , var = 3 );
C (exp value =10 , var = 2 );
D (exp value =10 , var = 1 ).
The probability that this project can be completed in 50 weeks lies in this range:
Select one:
0% to 34%
35% to 40%
60% to 65%
82% to 87%
93% to 96%
97% to 100%