Question: a project has been analyzed using the critical path period (cpm). the time for completing the project was determined to be 30 weeks. if the
a project has been analyzed using the critical path period (cpm). the time for completing the project was determined to be 30 weeks. if the time for one activity were reduced by 1 week (from 4 to week), which of the following best describes how the project completion time will be impacted?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
