Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A 100 0.13 B E 31

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A 100 0.13 B E 31 0.25 D 44 0.21 ID End 42 0.66 E End 22 0.75 What is the probability that the project will be completed within 190 days? a. 0.82 b. 0.18 C. 1 d. 0.25 e. 0