Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start AB A C 0.37 B E 58 0.25

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start AB A C 0.37 B E 58 0.25 D 19 0.14 D End 33 0.49 E End 14 0.75 What is the probability that the project will be completed within 127 days? 0.82 b. 0 O c. 0.25 O d. 1 O e. 0.18