Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 117 0.13 B E

A project has five activities with the durations
A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 117 0.13 B E 79 1 C D 46 0.23 D End 34 3.64 E End 20 0 What is the probability that the project will be completed within 205 days? a. 0.25 Ob. 0.18 C. 1 O d. 0 Oe. 0.82

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!