Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 14 0.36 B E

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 14 0.36 B E 10 0.25 C D 24 0.38 D End 33 0.26 E End 27 0.75 What is the probability that the project will be completed within 75 days? O a. 0 O b. 0.18 O c. 1 O d. 0.82 O e. 0.25

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!