A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point
Fantastic news! We've Found the answer you've been seeking!
Question:
A project has four major activities.
Activity A precedes activity B, activity C precedes activity D.
3-point estimates for activities are
A(9.5, 19, 28.5 ),
B( 4.5, 9, 13.5 ),
C( 2, 2, 2 ),
D( 3, 3, 3 ) weeks.
What probability would you assign to a project duration of more than 28 weeks?
Select one:
a. 0.3388
b. 1
c. 0.5
d. 0.8645
Related Book For
OM4 operations management
ISBN: 978-1133372424
4th edition
Authors: David Alan Collier, James R. Evans
Posted Date: