Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(11,22,33),B(7,14,21),C(1,2,3),D(17,34,51) weeks. What probability
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(11,22,33),B(7,14,21),C(1,2,3),D(17,34,51) weeks. What probability would you assign to a project duration of more than 36 weeks? a. 0.338 b. 0.5 c. 0.82 d. 0.75 Clear my choice