Question: Clear my choice A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(5,

Clear my choice A project has four major

Clear my choice A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(5, 10, 15 ), B(7, 14, 21 ), C(2, 4, 6), D( 10, 20, 30 ) weeks. What probability would you assign to a project duration of more than 24 weeks? O a. 0.853 O b. 0.5 O c. 0.22 O d. 0.75 Next page