Question: A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration

A project has the following activities, with

A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 1 day? Round your answers to 2 decimals. Activity PrecedentDuration Crash cost/day A 3 $350 B A 4.0 $250 A 6 $400 D B 6 $150 E B. 4.0 $200 F 4 $275 G D 5.9 $500 . E 8 $300