Question: A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?
\table[[,Time,\table[[Predecess],[or]]],[A,7,],[B,8,A],[C,13,B],[D,8,C],[E,7,A],[F,6,E],[G,6,A],[H,11,G],[L,12,H],[J,14,D, F, I]]