Question: A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity? Time Predecessor A 7 B 8 A C 13 B D 8 C E 7 A F 6 E G 6 A H 11 G I 12 H J 14 D, F, I