Question: A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity? Time Predecessor A 7 B 8 A C 13 B 8 C 7 F 6 E 6 11 G 112 H 14 D, F, I Select one: a. 13,7 b. 7,0 c. 7, 14 d. 13,36