Question: A project has three activities A , B , and C that must be carried out sequentially. The probability distributions of the times required to

A project has three activities A,B, and C that must be carried out sequentially. The probability distributions of the times required to complete each of the activities A,B, and C are uniformly distributed in intervals 1,5
2,3 and 3,6 respectively. Find the total project completion time and run 1000 simulation trials in Excel.
Question 1
1pts
The "project completion time" is a(n)...
Output of the simulation
Decision variable in the simulation
A fixed value in the simulation
 A project has three activities A,B, and C that must be