Question: A project has three activities A, B, and C that must be carried out sequentially. ----- A -----> ----B----> ------C------> The probability distributions of the
A project has three activities A, B, and C that must be carried out sequentially.
----- A -----> ----B----> ------C------>
The probability distributions of the times required to complete each of the activities A, B, and C are uniformly distributed in intervals (1,5], (2,8] and (3,6] days respectively.
The project completion time is the sum of times to finish all three activities.
Run 1000 simulation trials in Excel to simulate the project.
The project completion time is a(n)
Select one:
a. Decision variable in the simulation
b. Input of the simulation
c. A fixed value in the simulation
d. Output of the simulation
Step by Step Solution