Question: A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete activities

A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete activities A, B, and C are uniformly distributed in intervals [1,5], [2,3] and [3,6] respectively. Run at least 100 simulations in Excel.

The estimated mean project duration is:

The estimated variance of the project duration is

Please explain detail ( Excel)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!