Question: The Maze project has three paths. A - B - C has a length of 21 days. A - D - C has a length

The Maze project has three paths. A - B - C has a length of 21 days. A - D - C has a length of 18 days. Finally, A - E - C has a length of 19 days. Which one of the following statements is TRUE?

A. A - B - C is the critical path

B. A - E - C has the most slack

C. The expected duration of this project is 19 days

D. The expected duration of this project is 21 + 18 + 19 = 58 days