Question: A project has three paths. A-B-C has a length of 20 days. A-D-C has a length of 30 days. Finally, A-E-C has a length of

A project has three paths. A-B-C has a length of 20 days. A-D-C has a length of 30 days. Finally, A-E-C has a length of 25 days. Which one of the following statements is true?

Group of answer choices

The expected duration of this project is 20 days.

The expected duration of this project is 20 + 30 + 25 = 75 days.

A-D-C has the most slack.

A-D-C is the critical path.

Step by Step Solution

There are 3 Steps involved in it