Question: h A particular project notwork has two paths through it: Path A and Path B. Path A has an expected complotion time of 15 weeks

h
h A particular project notwork has two paths
A particular project notwork has two paths through it: Path A and Path B. Path A has an expected complotion time of 15 weeks and a variance in completion time of 8 weeks, while Path 8 has an expected completion time of 16 weeks and a variance in completion time of 4 woeks. What is the probablity that this project is going to take mote tban 10 neeks? a. 62% b. 28% C. 1004 d. 72% e.38\%