Question: d. 0.33 e. 0.67 QUESTION 6 A particular project network has two paths through it: Path A and Path B. Path A has an expected

d. 0.33 e. 0.67 QUESTION 6 A particular project
d. 0.33 e. 0.67 QUESTION 6 A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 15 week and a variance in completion time of 8 weeks, while Path B has an expected completion time of 16 weeks and a variance in completion time of 4 weeks. What is the probability that this project is going to take more than 18 weeks? a. 38% b.28% c. 62% d. 100% e. 72% Click Save and Submit to save and submit. Click Save All Answers to save all answers