Question: A project is in its 50 th week and has an actual cost of $900,000 for the work performed to date. The budgeted cost of

A project is in its 50th week and has an actual cost of $900,000 for the work performed to date. The budgeted cost of that work is $600,000. It expected to have completed $2,000,000 worth of work by this time. The budget for the entire project is $10,000,000. What is the:

a. CV

b. SV

c. CPI

d. EAC (provide two possible values. Show the formulas you use in calculating each)