Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 7 5

Given is a CPM project network diagram as shown below.

Activity

Start

A

B

C

D

E

F

G

H

End

days

0

7

5

8

5

8

4

2

8

0

a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days.. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)

Given is a CPM project network diagram as shown
s/assessment/take/launch.jsp?course_assessment_id=_109121_1&course_id=_3662 ion Completion Status: 26 3 4 QUESTION 1 iven is a CPM project network diagram as shown below. F Start H End m B D G Activity days B Start 0 A 7 E D 5 Al 5 8 8 G 2 a) The Project Completion time = 33 days. b) The Earliest Start time, ES, of Activity G- 23 days.. c) The Latest Finish time, LF, of Acitivity C = 15 days. d) The critical activities are - ACEGH (ex. Fill in answer as: ABCD) Click Save and Submit to save and submit. Click Save All Answers to save all answers

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!