Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 1.35 3.65
Given is a PERT project network diagram as shown below.
| Activity | Start | A | B | C | D | E | F | G | H | End |
| Time | 0 | 1.35 | 3.65 | 4.32 | 7.36 | 8.25 | 1.39 | 4.68 | 3.25 | 0 |
a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = (in 2 decimal places) d) The critical activities are = (ex. type in critical activities as ABCD, no comma, no space)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts